Current Build Project
Start Date: December 5, 2009
Family: The Thomason Family
Location: 212 N. Rehoboth Blvd, Milford
Status: Drywall!



Click picture to view our photo gallery. Go find yourself on our builds!

Build In Progress!

We have had a few snowdays, but we're keeping on schedule! Currently, we're finishing up the final touches to the outside of the home and completing construction on the front and side porches. The roof is complete and the main house has all of the siding finished. Ahead for the schedule will be moving into the interior to begin drywall once the electrical has been taken care of.

 